Question

1 Approved Answer

You are halfway through a project that has a budget of $ 1 0 0 , 0 0 0 . The CPI is 0 .

You are halfway through a project that has a budget of $100,000. The CPI is 0.9 and the SPI is 1.06. The customer has set a strict project deadline of 85 days for completion. As you review the project schedule you notice that one of your paths has a total float of 11 days and another has a total float of 14 days. Your critical path has a total duration of 55 days, and one of your activities has a free float of 5 days. What is the project float? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A 30 days option B 14 days option C 0 days option D 25 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Healthcare Project Management

Authors: Kathy Schwalbe, Dan Furlong

2nd Edition

1976573270, 978-1976573279

More Books

Students also viewed these General Management questions