You are in charge of the Aurora project. Given the following project network, baseline, and status information, develop status reports for periods 1-8 and complete
You are in charge of the Aurora project. Given the following project network, baseline, and status information, develop status reports for periods 1-8 and complete the performance indexes table. Calculate the EACf and VACf. Based on your data, what is the current status of the project? At completion?
Part B. You have met with your Aurora project team and they have provided you with the following revised estimates for the remainder of the project: Activity F will be completed at the end of period 12 at a total cost of $500. Activity G will be completed at the end of period 10 at a total cost of $150. Activity H will be completed at the end of period 14 at a total cost of $200.
Calculate the EACre and VACre. Based on the revised estimates, what is the expected status of the project in terms of cost and schedule? Between the VACf and the VACre, which one would you have the greatest confidence in? EACre = _________________VACre = _________________
Part A: Calculate the BAC, EV, AC, PV, CV, SV, EAC, ETC, and TCPI at the end of period 8.
Part B: Calculate the BAC, EV, AC, PV, CV, SV, EAC, ETC, and TCPI at the end of period 14.
The Questions are the ones that are in bold.
Kindly help me with the answer with the path to the solution. Highly appreciate your efforts. Thumps-up Guaranteed.
The already existing answer in the website is wrong as the values do not match the ones given in the question.
Thank You
Best regards.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started