Question
You are managing a project to renovate a kitchen for a client. The project calls for the removal of the existing cabinets and appliances and
You are managing a project to renovate a kitchen for a client. The project calls for the removal of the existing cabinets and appliances and then the installation of the new kitchen. You are provided the following information.
Activity | Duration Estimate | Comments |
Start the project | 0 day | |
Design the new kitchen | 1 week | |
Order the new cabinets | 1 day | 6 weeks delivery |
Order the new appliances | 1 day | 4 weeks delivery |
Turn off water & remove old plumbing | 1 day | |
Turn off power & remove old electrical | 1 day | |
Remove the old appliances | 1 day | |
Remove the old cabinets | 2 days | |
Rough in plumbing for new fixtures | 2 days | |
Rough in electrical for new fixtures | 2 days | |
Fix drywall | 1 week | |
Paint kitchen | 2 days | |
Install new cabinets | 2 days | |
Finish plumbing | 1 day | |
Finish electrical | 1 day | |
Install new appliances | 1 day | |
Finish the project | 0 day |
The project planned start date is Oct. 10th, 2022.
Resource | Cost |
Kitchen Designer | $60/hour |
Cabinets | $25,000 |
Appliances | $15,000 |
Paint | $500 |
Drywall | $600 |
Plumbing Fixtures | $3,000 |
Electrical Fixtures | $1,500 |
Plumber | $80/hour |
Electrician | $80/hour |
Cabinet Installer | $45/hour |
Painter | $40/hour |
General Contractor | $65/hour |
Drywaller | $40/hour |
Create a RACI for this project.
Create a cost estimate for the project including the basis of estimates.
Create a schedule network diagram and identify the critical path.
Create a budget s-curve for this project with upper and lower control limits
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started