you are managing two projects from a single Business Unit. The two projects are regarded as strategically beneficial and are equally important to your organisation
you are managing two projects from a single Business Unit. The two projects are regarded as strategically beneficial and are equally important to your organisation and are both complete. The project director has requested earned value data on these two concurrent projects from you. You provide the following information to your director:
Project A:
PV:
EV:
AC:
Project B:
PV:
EV:
AC:
After reviewing the data provided to him, the project director considers to shift some resources from project A to project B to speed up the second project which is currently behind schedule.
What is the most likely outcome of such a measure?
Question Select one:
a
To increase time efficiency Changing team assignments during late course of a project typically increases time efficiency
b
To increase cost efficiency Changing team assignments during late course of a project typically increases cost efficiency.
c
According to the law of diminishing returns, the consolidated cost variance of the two projects will decrease.
d
According to the law of diminishing returns, the consolidated cost variance of the two projects will increase.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started