You are monitoring your project schedule and are trying to determine how much work you got done for the amount of money you spent. Which
You are monitoring your project schedule and are trying to determine how much work you got done for the amount of money you spent. Which of the following would give you that information? a the planned value b the actual cost c the earned value d the schedule performance index