Question
You are negotiating a non-competitive contract for the production of replacement parts for equipment produced by Perry Products to meet unique Government requirements. Perry's cost
You are negotiating a non-competitive contract for the production of replacement parts for equipment produced by Perry Products to meet unique Government requirements. Perry's cost proposal includes an estimated direct labor cost of $49,000 (5,000 labor hours at $9.84 per hour). The estimate is based on the following direct manufacturing labor information:
Labor Category Labor Rate Projected Labor Hours
Team Leader $14.50 250
Assembly $8.20 2000
Fabrication $7.50 1500
Production $9.00 750
QC/Test $10.00 500
Totals 5000 1. Using the above info, what weighted-average direct manufacturing labor rate should you use in preparing your manufacturing direct labor cost objective? 2. Using the above info, what should be your direct manufacturing labor cost objective for this contract?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started