Question
You are on a project team to create a website with a project budget of $400,000. There are 8 planned iterations to deliver 240 initial
You are on a project team to create a website with a project budget of $400,000. There are 8 planned iterations to deliver 240 initial story points (the backlog) with each iteration expected to deliver 30 story points. Fill in the follow table below to determine project status. At the end of iteration 4 there is a project review.
What is the Cost Variance, Schedule Variance, CPI, and SPI at this point in the project?
Create a burn down chart which shows the planned burndown of story points along with the actual completion for each iteration. Given the numbers you have calculated in the questions above as well as your burn down charts, is the project doing well or is it in trouble? How many iterations will be required to finish the project? What would you expect the budget overage to be?
Remaining Backlog Iteration Points in Points Points Planned Actual Earned Backlog Completed Added Value Cost for Value to (Cumulative) the Date Iteration and Cumulative for the Project $55K 240 30 210 $50K .125 or $55K $50K 210 25 185 $100K $50K .23 or S105K $91.6K 185 30 15 170 $150K S60K 30 $50K 5 20 10 $55K 6. 25 20 $30K 35 $45K 40 $50K 2.
Step by Step Solution
3.38 Rating (157 Votes )
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started