Question
You are on a project team to create a website with a project budget of $400,000. There are 8 planned iterations to deliver 240 initial
You are on a project team to create a website with a project budget of $400,000. There are 8 planned iterations to deliver 240 initial story points (the backlog) with each iteration expected to deliver 30 story points. Fill in the follow table below to determine project status
At the end of iteration 4 there is a project review. What is the Cost Variance, Schedule Variance, CPI, and SPI at this point in the project? Create a burn down chart which shows the planned burndown of story points along with the actual completion for each iteration. Given the numbers you have calculated in the questions above as well as your burn down charts, is the project doing well or is it in trouble? How many iterations will be required to finish the project? What would you expect the budget overage to be?
Iteration 2 3 4 5 6 7 8 Points in Backlog 240 210 185 Points: Points Completed Added 30 25 30 30 20 25 35 40 0 0 15 0 10 20 0 0 Remaining Backlog 210 185 170 Planned Value (Cumulative) $50K $100K $150K Actual Cost for the Iteration and Cumulative for the Project $55K $55K $50K $105K $60K $50K $55K $30K $45K $50K Earned Value to Date .125 or $50K 23 or $91.6K
Step by Step Solution
3.40 Rating (156 Votes )
There are 3 Steps involved in it
Step: 1
Question Itera Points in Points Points tion Backlog Completed Added 1 240 2 21...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Document Format ( 2 attachments)
636a609fab2b2_213822.pdf
180 KBs PDF File
636a609fab2b2_213822.docx
120 KBs Word File
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started