Question
You are one of three carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters
You are one of three carpenters assigned to complete a short construction project. Right before the start of the project, one of your fellow carpenters was hospitalized and will not be available to work on the project.
Develop a resource-constrained schedule in the loading chart that follows to see how long the project will take with only 2 carpenters. Be sure to record the order in which you schedule the activities using the scheduling heuristics.
*The solution to this exercise can be found in Appendix 1
Activities A, B, C, D, E, G, and H require 2 carpenters to complete. Activity F requires only 1 carpenter. No splitting of activities is possible.
You will receive a bonus if the project is completed within 15 days. Should you start planning how you will spend your bonus?
2 2 2 415 G| 10 0 20 82 10 2 A 2 5 D 2 020 022 020 2 c5 0 2 0 2 35 516 10 H| 12 11 1 73 10 O2 0 10 2 12 Legend ES ID EF SL Use the following heurtstics Minimum slack Smalest duration Lowest identirfication number LS DURLF Resource ID RES DUR ES LF SL 012 3 4 5 6 78 9 10 11 12 13 14 15 16 17 18 A 2 2 B 2 1 C2 3 D 21 E 22 F1 3 G 2 2 H 2 Rescurces scheduled Resources available 2 2 2 2 2 2 22 2 2 2 222 |2 2 2 2
Step by Step Solution
3.41 Rating (164 Votes )
There are 3 Steps involved in it
Step: 1
solution of this problem is attache below Note the fo...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started