You are one of three carpenters assigned to complete a short construction project. Right before the start
Question:
Develop a resource-constrained schedule in the loading chart that follows to see how long the project will take with only 2 carpenters. Be sure to record the order in which you schedule the activities using the scheduling heuristics. Activities A, B, C, D, E, G, and H require 2 carpenters to complete. Activity F requires only 1 carpenter. No splitting of activities is possible. You will receive a bonus if the project is completed within 15 days. Should you start planning how you will spend yourbonus?