Question

1 Approved Answer

You are planning an excavation activity using a hydraulic excavator with a bucket capacity of 3 CY and a maximum digging depth of 25 feet.

You are planning an excavation activity using a hydraulic excavator with a bucket capacity of 3 CY and a maximum digging depth of 25 feet. The material for this excavation is a well blasted rock giving a bucket fill factor of 75% and a swell percent of 60%. The swing angle is 50 and the average depth of the cut is 14 feet. The cost of the excavator and operator is $230/hr and on this operation a 45 minute hour is anticipated. The standard cycle times (including adjustment for dumping into a truck) for this machine are as follows:

  • Load time - 7 seconds
  • Swing loaded time - 6 seconds
  • Dump bucket - 5 seconds
  • Swing empty - 4 seconds

What is the cost per Bank Cubic Yard to excavate this material? Round your answer to the nearest thousandth.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management

Authors: Richard Lynch

5th Edition

0273716387, 978-0273716389

More Books

Students also viewed these General Management questions

Question

5. How do unions affect the natural rate of unemployment?

Answered: 1 week ago