You are the new project manager tasked with taking over for a projectmanagerwho left six weeks ago. Some of the numbers that you find in

  1. You are the new project manager tasked with taking over for a projectmanagerwho left six weeks ago. Some of the numbers that you find in your initial research are as follows:

A)Estimated project cost: $675,000

B)Project timeline: 24 weeks

C)This is week 16 and accumulated costs are $300,000.

D)Additionally, only 25% of the work has been completed.

What is the cost variance?

What is the schedule variance?

What will be the estimated costat completion?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

To calculate the cost variance CV schedule variance SV and estimated cost at completion EAC we can u... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Information Technology For Managers

Authors: George Reynolds

2nd Edition

1305482492, 1305389832, 9781305482494, 978-1305389830

More Books

Students also viewed these Accounting questions

Question

What is a covariate?

Answered: 1 week ago