Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

You are the Owners project manager on an electrical upgrade project. Existing overhead power lines are being buried in a duct bank to hide them

You are the Owners project manager on an electrical upgrade project. Existing overhead power lines are being buried in a duct bank to hide them from view in an area of the town that is being revitalized. There are a total of 8.6 miles of power lines being buried. All the power lines being buried are on one street and run in a straight line. Due to the size of the wires, a pull box needs to be installed every 500 feet.

There are three primary activities in burying the power lines:

Dig and install pull box/conduit

Pull wires

Terminate/connect wires

Labor:

A four-man crew can install one pull box and 500 ft of conduit in 2 days.

A seven-man wire crew can test and install 1000 ft of wire per day.

A three-man electrician crew can terminate 7 connections per day.

Task

Draw an LOB diagram to illustrate how it works. Submission can be handwritten and uploaded or created on the computer.

Submit a written explanation of what the LOB is going to tell/show the contractor and why it would be useful in this application.

pls solve this urgently i will upvote 3 members

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Accounting Information for Decision-Making and Strategy Execution

Authors: Anthony A. Atkinson, Robert S. Kaplan, Ella Mae Matsumura, S. Mark Young

6th Edition

137024975, 978-0137024971

More Books

Students also viewed these Accounting questions