You are the project manager of a project that has $142000 as the budget at completion. 65% of the work was planned to be completed
You are the project manager of a project that has $142000 as the budget at completion. 65% of the work was planned to be completed at the end of month seven but only 53% has been completed as at today with an actual cost of $78000. The project's Estimate To Completion (ETC) is closest to? 103755 O 138340 69170 O 51877 O None of the given answers