You are the scheduler in a machining shop for heavy parts. Four jobs will arrive at your workshop today. All of them need five

 

You are the scheduler in a machining shop for heavy parts. Four jobs will arrive at your workshop today. All of them need five operations in the same sequence: turning, milling, boring, grinding and polishing. The operation times (working days) are listed in the following table: Operations Turning Milling Boring Grinding Polishing Jobs A 15 5 6 10 10 5 B 6 13 15 7 5 C 11 7 8 5 7 D _ 12 18 _ 15 20 20 Please arrange the production schedule for these jobs, using Palmer's Algorithm. Please also draw a Gantt chart and calculate the makespan.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Job Turning Milling Boring Grinding Polishing A 15 5 6 ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Automation Production Systems and Computer Integrated Manufacturing

Authors: Mikell P.Groover

3rd edition

132393212, 978-0132393218

More Books

Students also viewed these General Management questions

Question

Is tire service system of WestJet JIT/lean?

Answered: 1 week ago

Question

What is value stream mapping and why is it important?

Answered: 1 week ago