Question

1 Approved Answer

You are thinking about shortening (i.e. crashing) the entire project. The information of the normal job times (i.e.e the minimum job time the job can

You are thinking about shortening (i.e. crashing) the entire project. The information of the normal job times (i.e.e the minimum job time the job can be crashed to), and the costs needed for shortening each job by one day is provided below (Table 2). You were just provided with a fund of $1,500 (besides the fund of completing the project w/o crashing). The objective is to crash the project as much as possible within $1,500. Under the objective, if there is some fund left that is not usable for crashing the project, you should save it. Show your method of crashing the project.

Table 2
Job label Job description Immediate predecessor(s) Normal time (days) Crash time (days) Cost to crash the job 1 day
A Planning -- 2 1 $450.00
B Purchasing A 6 4 $300.00
C Excavation A 10 7 $250.00
D Sawing B 3 2 $100.00
E Placement C, D 2 1 $400.00
F Assembly E 1 1 --
G Infill F 2 1 $430.00
H Outfill F 1 1 --
I Decoration G, H 3 2 $200.00

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Managerial Accounting Tools For Business Decision Making

Authors: Jerry J. Weygandt, Paul D. Kimmel, Ibrahim M. Aly, Donald E. Kieso

6th Canadian Edition

1119731828, 9781119731825

Students also viewed these Accounting questions