Question
You are thinking about shortening (i.e. crashing) the entire project. The information of the normal job times (i.e.e the minimum job time the job can
You are thinking about shortening (i.e. crashing) the entire project. The information of the normal job times (i.e.e the minimum job time the job can be crashed to), and the costs needed for shortening each job by one day is provided below (Table 2). You were just provided with a fund of $1,500 (besides the fund of completing the project w/o crashing). The objective is to crash the project as much as possible within $1,500. Under the objective, if there is some fund left that is not usable for crashing the project, you should save it. Show your method of crashing the project.
Table 2 | |||||
Job label | Job description | Immediate predecessor(s) | Normal time (days) | Crash time (days) | Cost to crash the job 1 day |
A | Planning | -- | 2 | 1 | $450.00 |
B | Purchasing | A | 6 | 4 | $300.00 |
C | Excavation | A | 10 | 7 | $250.00 |
D | Sawing | B | 3 | 2 | $100.00 |
E | Placement | C, D | 2 | 1 | $400.00 |
F | Assembly | E | 1 | 1 | -- |
G | Infill | F | 2 | 1 | $430.00 |
H | Outfill | F | 1 | 1 | -- |
I | Decoration | G, H | 3 | 2 | $200.00 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started