You have approached the management for additional funding for your project. In your presentation, you have captured these critical parameters. BAC = $120,000 PV =
You have approached the management for additional funding for your project. In your presentation, you have captured these critical parameters.
BAC = $120,000 PV = $50,000 AC = $50,000 CPI = 0.8
But, one person in the audience requested for Cost Variance. What should be your response?