Question

1 Approved Answer

You have just studied the raw material acquisition process within your organization. Through a Value Stream Analysis, you have determined that the process time is

You have just studied the raw material acquisition process within your organization.

Through a Value Stream Analysis, you have determined that the process time is comprised with the following elements (a) CVA of 2.5 hour (b) BVA of 2 hours, and (c) NVA of 7 hours.

What is the PCE of the process? How does this compare to other transactional processes?

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Management A Managerial Approach

Authors: Jack R. Meredith, Samuel J. Mantel Jr.

8th edition

470533021, 978-0470533024

More Books

Students also viewed these General Management questions