Question

1 Approved Answer

You have just used the network planning model and found the critical path length is 3 0 days and the variance of the critical path

You have just used the network planning model and found the critical path length is 30 days and the variance of the critical path is 25 days. What is the probability that the project will be completed in 33 days or less equal to?(2 decimal accuracy).
Multiple Choice
0.73
0.55
0.12
0.27
0.60

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Management Today

Authors: Terri A. Scandura, Kim Gower

1st Edition

1506385877, 978-1506385877

More Books

Students also viewed these General Management questions

Question

What is the first lesson from financial market history?

Answered: 1 week ago