Question
1 Approved Answer
You have prepared the following schedule for a project in which the key resource is an information kiosk. This schedule is contingent on having 4
You have prepared the following schedule for a project in which the key resource is an information kiosk. This schedule is contingent on having 4 information kiosks. You receive a call from you partner, Gates, who desperately needs one of you information kiosks. You tell Gates you would be willing to let him have the information kiosk if you are still able to complete you project in 13 months.
0 1 2 2 4 3 ES ID EF 4 1 4 4 1 4 SL RES SL 4 2 6 6 1 7 LS DUR LF 0 2 3 3 5 7 0 1 0 0 1 0 0 3 3 3 4 7 7 6 11 0 2 0 0 3 3 7 4 11 0 2 0 0 3 3Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started