You have released your RFP on the GPE; it is a five year aircraft maintenance contract for a fleet of 25 aircraft. Two weeks later
You have released your RFP on the GPE; it is a five year aircraft maintenance contract for a fleet of 25 aircraft. Two weeks later the Program Manager tells you the requirement has changed; they now need only one year's worth of maintenance and the size of the fleet has been reduced to 5 aircraft. What should you do with your solicitation