Question

1 Approved Answer

You may need to use the appropriate technology to answer this question. Consider the PERT / CPM network with estimated times in weeks shown in

You may need to use the appropriate technology to answer this question.
Consider the PERT/CPM network with estimated times in weeks shown in the following figure. The project is scheduled to begin on May 1.
The three-time estimate approach was used to calculate the expected times and the following table gives the variance for each activity.
(a) Give the expected project completion date and the critical path. (Enter your critical path as a comma-separated list.)
The expected project completion is
weeks from May 1 with a critical path of
(b) Based only on the critical path, by what date are you 99% sure the project will be completed? (Round your answer to one decimal place.)
weeks from May 1.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Management Managing Across Borders And Cultures Text And Cases

Authors: Helen Deresky

9th Global Edition

1292153539, 978-1292153537

More Books

Students also viewed these General Management questions