You need to perform a quick ETC. The current Cost Performance Report indicates BAC=$1,900,500 EV=$455,000 SPI = 1.0 CPI = .941 AC = $483,300. Finance
You need to perform a quick ETC. The current Cost Performance Report indicates
BAC=$1,900,500
EV=$455,000
SPI = 1.0
CPI = .941
AC = $483,300.
Finance has indicated that CPI & SPI will influence the remaining work
How much funding is required to complete the remaining project activities (ETC)?
Group of answer choices
A $2,019,432
B $1,536,132
C $1,052,931
D $1,334,463