Question

1 Approved Answer

. Your company completed the East Side subdivision. The costs are shown in Figure 11-4. The site concrete labor and outside lighting were done by

. Your company completed the East Side subdivision. The costs are shown in

Figure 11-4. The site concrete labor and outside lighting were done by

subcontractors. The grading and excavation, sanitary sewer, water line, and

storm drain were done by the companys excavation crew. The companys

minimum profit and overhead markup is 15%. Determine the profit

generated by the estimator, project management, and the excavation crew

on this project.

Job: 424 East Side Subdivision Sept. 1, 2004

Contract Billed --------------------Costs----------------------

Code Description Amount to Date Actual Budget Overrun

2100 Grading & Excavation 57,800 59,000 -1,200

2400 Sanitary Sewer 27,365 28,200 -835

2450 Water Line 31,750 31,000 750

2500 Storm Drain 16,850 17,000 -150

2610 Site Conc.-Labor 19,200 19,200 0

2620 Site Conc.-Concrete 21,265 20,900 365

2900 Outside Lighting 23,600 23,600 0

Job Total 234,699 234,699 197,830 198,900 1,070

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Internal Quality Systems Auditing

Authors: Paul F. Lewis

1st Edition

1570744076, 978-1570744075

Students also viewed these Accounting questions