Your manufacturing company is interested in developing a cost model to price a AM part that will be manufactured for production. Based on data that

Your manufacturing company is interested in developing a cost model to price a AM part that will be manufactured for production.
Based on data that they have collected:
Machine and ancillary equipment cost : $1,000,000
Equipment depreciation cost per year : $130,000
Machine Maintenance cost per year: $50,000
Machine operator cost per hour : $40hr
Set up and prep time for each build : 30min
Post processing time per build: 1hr
Material Cost per Kg: $275kg
They estimate the following:
a. Number of parts made per year: 60,000
b. Each build can build 200 parts simultaneously on a single platform
c. Build time for each platform of 200 parts: 25 hrs
d. The factory will run 247 for 200 days in a year.
Under this scenario what will be the cost per part?
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Transport Operations

Authors: Allen Stuart

2nd Edition

978-0470115398, 0470115394

More Books

Students also viewed these General Management questions