Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: 51.200.000. EV: 51.000.000. AC: $1.200.000 You
Your project exceeded costs in the past caused by an underestimation of resource costs in the cost baseline: PV: 51.200.000. EV: 51.000.000. AC: $1.200.000 You expect the underestimation to influence the future as much as it did in the past. If the value of the remaining work (BAC - EV) is at 51.000.000, what should be your new EAC (estimate at completion)? A) $1.800.000 B) $2.000.000 C) $2.200.000 D) $2.400.000