Question
You've volunteered to make bird houses, at your own expense and on your own time, to be offered for sale at your daughter's high school
You've volunteered to make bird houses, at your own expense and on your own time, to be offered for sale at your daughter's high school fair to raise money for new sports equipment. You have three different designs in mind. You estimate the first design will require about $5 in material cost and about two hours of work. The second design is a little more elaborate and will require about $10 in material cost and three hours of work. The last design, more elaborate yet, will require about $15 in material cost and four and a half hours of work.
There are about 5 weeks remaining until the school fair. You figure you can safely work an average of between 35 and 40 hours per week (week day nights and weekends) and you only have $600 available to complete the project. After doing some expected value calculations, you conclude the best product mix is 25 birdhouses using the first design, 20 birdhouses using the second design, and 15 birdhouses using the third design. You develop a construction plan as follows:
The calculated planned budget for each week of the project and for the total project is:
Answer:
Calculate the planned budget for each week of the project and for the total project.
WEEK First Second Third Project Cost
1 7 4 2 105
2 4 4 3 105
3 7 3 3 110
4 4 4 4 120
5 3 5 3 110
Total $550
2.At the end of week 2, you look at your actual progress and find the following:
WeekFirstSecondThirdProject Cost1742$1052443$1053733$1104444$1205353$110Total$550
2.Earned Value= 40% x $550 =$220
The earned value of the project for the first two weeks is $220.
Theproject to-dateis40%.
Explanation:
1. Multiply each design by the material cost per design which are $5, $10, and $15, for the first to third design, respectively. To get the total project cost, you can add the project cost per week. Another way is that multiply each total design with the corresponding material cost, e.g., 25 x $5; 20 x $10; and 15 x $15.
Formula forEV= Percent Complete (actual) x Task Budget
Since there are 2 weeks, the percentage of completion or the project to-date is 40%. (2weeks/5weeks=0.4 x 100= 40%)
Question:
Assuming you continue working as you are without making any changes to your processes or materials, what is the forecast of total project cost? Will you exceed your total available funds?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
To forecast the total project cost we can use the earned value EV method which compar...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started