The duration of a construction activity was estimated to be in the range [2, 6] days with

Question:

The duration of a construction activity was estimated to be in the range [2, 6] days with a most likely duration of 4 days. A construction engineer used the following symmetric density function to model the duration:image text in transcribed

Determine the necessary constants a and b to have a legitimate density function. Graph both the density and cumulative functions.

Step by Step Answer:

Related Book For  book-img-for-question
Question Posted: