The following represents a process used to assemble a chair with an upholstered seat. Stations A, B,

Question:

The following represents a process used to assemble a chair with an upholstered seat. Stations A, B, and C make the seat; stations J, K, and L assemble the chair frame; station X is where the two subassemblies are brought together; and some final tasks are completed in stations Y and Z. One worker is assigned to each of the stations. The line is paced using a countdown clock to synchronize production at each station. Generally, there is no inventory kept anywhere in the system, although there is room for one unit between each of the stations that might be used for a brief amount of time.

Given the following amount of work in seconds required at each station:

A 38 J 32 X 22 B 34 K 30 Y 18 C 35 L 34 Z 20

a. What is the possible daily output of this “process” if eight hours of processing time is available each day?

b. Given your output rate in part (a), what is the efficiency of the process?

c. What is the flow time of the process?

LO11-2

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

ISE Operations And Supply Chain Management

ISBN: 9781260575941

16th International Edition

Authors: F. Robert Jacobs, Richard B. Chase

Question Posted: