4. We know that Blue Pad Companys lead time L is one week and demand rate is...

Question:

4. We know that Blue Pad Company’s lead time L is one week and demand rate is 100 units per week. Compute the amount of Safety Stock and new ROP assuming that the company desires a 98% service level. Standard deviation of demand over lead time is eight.