=+1. Consider the following project activities: ACTIVITY DURATION (DAYS) PREDECESSORS A 3 None B 2 None C
Question:
=+1. Consider the following project activities:
ACTIVITY DURATION
(DAYS) PREDECESSORS A 3 None B 2 None C 6 A D 1.5 A, B E 2.5 C, D F 3.5 D G 4 E, F