11. Ms. Mona Hull is in charge of a project to build a 50-foot yacht for a...

Question:

11. Ms. Mona Hull is in charge of a project to build a 50-foot yacht for a wealthy industrialist from Jasper, Indiana. The yacht is scheduled to compete in the famous Lake Lemon Cup Race. Eight weeks remain for constructing the yacht. Assume that each week consists of 5 workdays, for a total lead time of 40 days. The work required to complete the yacht comprises 10 operations, 4 days for each including move time between operations.

a. On Tuesday morning of week 3, 3 of the 10 operations had been completed and the yacht was waiting for the fourth operation. What is the critical ratio priority?

b. What is the critical ratio priority if only 2 of the 10 operations are completed by Tuesday morning of week 3?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management The CPIM Reference

ISBN: 9781265138516

3rd Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: