12. Big Dans Machine Shop is considering the use of a priority scheduling rule in the fabrication...
Question:
12. Big Dan’s Machine Shop is considering the use of a priority scheduling rule in the fabrication shop and must decide whether to use: (1) critical ratio, (2) earliest due date, (3) shortest operation next, or (4) order slack. The current shop status of the company is given here:
a. Using the four sequencing rules, compute the scheduling priority for each order given in the table above.
b. What order should be run first under each of these scheduling rules?