12. Big Dans Machine Shop is considering the use of a priority scheduling rule in the fabrication...

Question:

12. Big Dan’s Machine Shop is considering the use of a priority scheduling rule in the fabrication shop and must decide whether to use: (1) critical ratio, (2) earliest due date, (3) shortest operation next, or (4) order slack. The current shop status of the company is given here:

image text in transcribed

a. Using the four sequencing rules, compute the scheduling priority for each order given in the table above.

b. What order should be run first under each of these scheduling rules?

image text in transcribed