11. Suppose management at Spartan Cabinets has developed additional information for the project described in Problem 10....
Question:
11. Suppose management at Spartan Cabinets has developed additional information for the project described in Problem 10.
To illustrate, Activity A can be crashed by up to three weeks at a cost of $2,000 per week. Therefore, Activity A can be 8, 7, 6, or 5 weeks long, depending on how much money Spartan Cabinets decides to spend to crash the activity.
a. (***) What is the cheapest way to crash the project by two weeks?
b. (***) What is the shortest time in which the project can be completed? (Assume that cost is not a concern.)