=+12. As you must have noticed in the product structure of problem 11, Hangers appears in two

Question:

=+12. As you must have noticed in the product structure of problem 11, Hangers appears in two subassemblies: Frame Backing and Wooden Frame & Hanger. Based on the same order information for Photo Frame AAA for weeks 10, 12, and 14, complete the MRP table for Hangers below.

Note: First you would need to use the MRP records for Frame Backing, developed in problem 11 and then complete the MRP records for Wooden Frame & Hanger below.

FRAME BACKING WEEK 9 10 11 12 13 14 Required: 1 Gross requirements 500 500 500 LT (weeks): 1 Scheduled receipts Projected ending inventory: 100 Net requirements Min. order: 50 Planned receipts Planned orders