13. Complete the following MRP time-phased record: The following events occurred during week 1: 1. Actual demand
Question:
13. Complete the following MRP time-phased record:
The following events occurred during week 1:
1. Actual demand during week 1 was only 5 units.
2. A scheduled receipt of 45 was received during week 1.
3. A cycle count of on-hand units showed 17 units at the start of week 1.
4. Marketing forecasted that 40 toasters would be required in week 9.
Update the record below after rolling through time.