12. Consider the following MRP record: Suppose 15 units of the scheduled receipt for 50 units due...

Question:

12. Consider the following MRP record:

image text in transcribed

Suppose 15 units of the scheduled receipt for 50 units due on Monday of week 2 are scrapped during week 1, and no scrap ticket is issued.
Furthermore, assume this lot is not counted before it is put away in the stockroom on Monday of week 2, but is recorded as a receipt of 50 units.
What impact will these actions have on factory operations?