17. Shown next is the MRP record for part no. 483. The current shop day is 100...

Question:

17. Shown next is the MRP record for part no. 483. The current shop day is 100 (with five-day weeks); it is now Monday of week 1. Open orders

(scheduled receipts) are due Mondays (shop days 100, 105, 110, 115, etc.) of the week for which they are scheduled. The shop floor has just reported that the batch of 40 on shop order number 32 has just finished at machine center A43 and is waiting to be moved to C06. It takes one day to move between machine centers (or to I02, the inventory location) and one day of queue time at the machine centers. (The inventory location does not require the queue time, but one day of

“machine time” is shown for clearing the paperwork.) Part number 483’s routing and status are also given.

image text in transcribed

a. Use a spreadsheet to replicate the MRP record and calculate the critical ratio for part no. 483. Should the planner take any action?

b. What would the priorities be if the inventory were 23 instead of 20?
What action should be taken now?

c. What if inventory were 17 instead of 20?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management The CPIM Reference

ISBN: 9781265138516

3rd Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: