=+3. Consider the following project activities: ACTIVITY DURATION (DAYS) PREDECESSORS A 4 None B 3 A C

Question:

=+3. Consider the following project activities:

ACTIVITY DURATION

(DAYS) PREDECESSORS A 4 None B 3 A C 7 A D 9 A E 8 A F 7 B G 6 C H 13 C I 4 D, E J 12 E K 1 E L 5 F, G, H M 4 I, J, K N 5 L, M

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer: