5. Nino Spirelli has constructed the following (partial) time-phased MPS record: a. Complete the record. b. Are
Question:
5. Nino Spirelli has constructed the following (partial) time-phased MPS record:
a. Complete the record.
b. Are there any problems?
c. What is the earliest Nino can promise an order for 44 units?
d. Assume that an order for 15 is booked for week 4. Assume the order for 44 units in part c is not booked; recompute the record.