7. Toms Sailboard manufactures custom wind surfers in Seattle. The incoming orders follow different routes through the

Question:

7. Tom’s Sailboard manufactures custom wind surfers in Seattle. The incoming orders follow different routes through the shop, but all orders must stop at each of the three work centers (WCs) in the plant. The following table contains information regarding the four jobs that arrive over five days and need to be scheduled at the company. It is currently November 10 and Tom works a seven-day week.

image text in transcribed

Assume that the material for all orders is ready for processing as soon as the orders arrive and that a first-come/first-served sequencing rule is used at all work centers. All three work centers are idle as work begins on orders B and G on November 10.

a. Construct a Gantt chart depicting the processing and idle times for the three work centers for these four jobs.

b. How many days does each job wait in queue for processing at work center 2?

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management The CPIM Reference

ISBN: 9781265138516

3rd Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: