8. The production manager at the Knox Machine Company is preparing a production schedule for one of...

Question:

8. The production manager at the Knox Machine Company is preparing a production schedule for one of the fabrication shop’s machines, the P&W grinder. He has collected the following information on jobs currently waiting to be processed at this machine. (There are no other jobs, and the machine is empty.)

image text in transcribed

a. The production manager has heard about three dispatching rules: the shortest operation next rule, the first-come/first-served rule, and the earliest due date rule. In what sequence would these jobs be processed at the P&W grinder if each rule were applied?

b. If it is now the morning of July 10 and the shortest operation next rule is used, when would each of the four jobs start and be completed on the P&W grinder? (Express your schedule in terms of the calendar dates involved, assuming that there are seven working days each week.)

Fantastic news! We've Found the answer you've been seeking!

Step by Step Answer:

Related Book For  book-img-for-question

Manufacturing Planning And Control For Supply Chain Management The CPIM Reference

ISBN: 9781265138516

3rd Edition

Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann

Question Posted: