=+9. (**) Develop two exponential smoothing forecasts for periods 2 through 11. For the first forecast, use
Question:
=+9. (**) Develop two exponential smoothing forecasts for periods 2 through 11. For the first forecast, use a = 0.2. For the second, use a = 0.7. Assume that your forecast for period 1 was 250. Plot the results. Which model appears to work better? Why?