9. Identifying bottlenecks is most often accomplished with a. Capacity requirements planning b. Rough-cut capacity planning c.
Question:
9. Identifying bottlenecks is most often accomplished with
a. Capacity requirements planning
b. Rough-cut capacity planning
c. Value stream analysis
d. Material requirements planning