=+ All scheduled receipts, lead times, and beginning inventory levels are shown. FRAME BACKING WEEK 9 10
Question:
=+• All scheduled receipts, lead times, and beginning inventory levels are shown.
FRAME BACKING WEEK 9 10 11 12 13 14 Required: 1 Gross requirements 500 500 500 LT (weeks): 1 Scheduled receipts Projected ending inventory: 100 Net requirements Min. order: 50 Planned receipts Planned orders M12_BOZA1581_05_GE_C12.indd 413 10/01/19 2:07 pm 414 PART IV ● PLANNING AND CONTROLLING OPERATIONS AND SUPPLY CHAINS MAT BOARD WEEK 9 10 11 12 13 14