=+b. (**) Every week of delay in the project costs your company $3,000. Suppose you know the
Question:
=+b. (**) Every week of delay in the project costs your company $3,000. Suppose you know the following:
(1) Activity G can be crashed by 1 week, at a cost of
$1,500; (2) activity F can be crashed by 1 week, at a cost of only $50; and (3) activity H can be crashed by