Which of the following is not and action commonly taken by an MRP planner? I. Release orders
Question:
Which of the following is not and action commonly taken by an MRP planner?
I. Release orders II. Confirm inventory counts on incoming shipments III. Reconcile MRP errors
a. I only
b. II only
c. III only
d. All are MRP planner actions
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Manufacturing Planning And Control For Supply Chain Management
ISBN: 9780071750318,9780071750325
1st Edition
Authors: F. Robert Jacobs, William Lee Berry, D. Clay Whybark, Thomas E. Vollmann
Question Posted: