A commitment to an external supplier (e.g., a purchase order) is represented in the material requirements planning

Question:

A commitment to an external supplier (e.g., a purchase order) is represented in the material requirements planning (MRP) system by a

a. Scheduled receipt

b. Planned order

c. Either a scheduled receipt or a planned order

d. Neither a scheduled receipt nor a planned order