A commitment to an external supplier (e.g., a purchase order) is represented in the material requirements planning
Question:
A commitment to an external supplier (e.g., a purchase order) is represented in the material requirements planning (MRP) system by a
a. Scheduled receipt
b. Planned order
c. Either a scheduled receipt or a planned order
d. Neither a scheduled receipt nor a planned order