Which of the following strategies can be useful in reducing material requirements planning (MRP) system nervousness? I.

Question:

Which of the following strategies can be useful in reducing material requirements planning (MRP) system nervousness?

I. Introducing system stability through time fences II. Careful use of lot-sizing procedures III. Using firm planned orders

a. I only

b. II only

c. I and II only

d. I, II, and III