The first project has a positive NPV of NPV = $50,000 + $250,000 1.25 + $467,500 1.252
Question:
The first project has a positive NPV of NPV = $50,000 +
−$250,000 1.25
+ $467,500 1.252
+
−$387,500 1.253
+ $120,120 1.254
≈ $1.15 The second project has an NPV of −$1.15. You should take project A, but not B. If you plot the NPV as a function of the interest, you will see that there are multiple IRRs for these projects, specifically at 10%, 20%, 30%, and 40%. With a cost of capital of 25%, you cannot easily determine which of these two projects you should take. Make your life easy, and just use NPV instead.
Fantastic news! We've Found the answer you've been seeking!
Step by Step Answer:
Related Book For
Question Posted: